Skip to main content
CityRuleLookup

Sandy, UT Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Enforcing agency
Sandy Public Works Department
Permit trigger
1+ acre of land disturbance
Criminal penalty
Class B misdemeanor, per day
Civil penalty
25% surcharge on City remediation
Appeal path
Director, then Mayor, then court
Governing section
City Code § 9-1-7

Summary

Sandy City Code Chapter 9-1, the Storm Water Quality and Enforcement ordinance, bars discharging pollutants into the City's storm drain system and requires SWPPPs for developments disturbing an acre or more. The Public Works Department enforces it with stop-work orders, notices of violation, and Class B misdemeanor charges for knowing violations.

No person shall discharge or cause to be discharged into the City storm drain system or watercourses any materials, including, but not limited to, pollutants or waters containing any pollutants, that cause or contribute to a violation of applicable water quality standards other than stormwater.

Full Breakdown

Sandy City Code Title 9, Chapter 9-1 (Storm Water Quality and Enforcement, retitled by Ordinance 21-11 in 2021) exists 'to protect the health, safety and welfare of Sandy City, its inhabitants, and downstream entities' by controlling what enters the municipal storm drain system (Section 9-1-1). Section 9-1-7 makes it unlawful to discharge or cause the discharge of any pollutant-bearing, non-stormwater material into the City's storm drains or watercourses, with narrow exceptions for things like landscape irrigation runoff, de-chlorinated pool water, foundation drains, and emergency firefighting water.

The same section separately bans hauling uncovered loads that can spill onto streets and requires anyone tracking mud, dirt, or debris onto pavement to remove it immediately. Section 9-1-8 requires a State Construction Stormwater Permit (an NOI from the Utah Division of Water Quality) and a Stormwater Pollution Prevention Plan for any project disturbing one acre or more, or that is part of a larger common development plan, plus a Stream Alteration Permit from the State Division of Water Rights and an EPA Section 404 wetlands permit where applicable; SWPPP review fees are set in the City's consolidated fee schedule and must be paid before a building permit issues.

The Public Works Department, acting through its Authorized Enforcement Agent, administers the chapter (Section 9-1-4) and can issue a stop-work order, a written notice of violation demanding cleanup or monitoring, or refer a violation for nuisance abatement (Section 9-1-10). A knowing, reckless, or intentional violation is a Class B misdemeanor, with each day of continuing violation a separate offense, and the City can also draw on an applicant's posted compliance bond (Section 9-1-11). Decisions can be appealed first to the Public Works Director, then to the Mayor, and finally to District Court (Section 9-1-12).

Violations & Fines

A stormwater violation starts with a written notice of violation or an immediate stop-work order from Public Works; failing to correct it can bring nuisance-abatement action and a Class B misdemeanor charge, with each day of continued violation counted separately. The City can also draw on the developer's compliance bond and charge a 25 percent penalty on top of the cost of any erosion-control work it has to perform itself.

Frequently Asked Questions

What can't I put in Sandy's storm drains?
Section 9-1-7 bans discharging any pollutant, including paint, automotive fluids, yard waste, or sewage, into the City's storm drain system or watercourses. Limited exceptions exist for things like landscape irrigation overflow, de-chlorinated swimming pool water, foundation drain water, and water used for emergency firefighting.
Do I need a stormwater permit to build in Sandy?
If your project disturbs one acre or more, or is part of a larger phased development, Section 9-1-8 requires a State Construction Stormwater Permit (NOI) from the Utah Division of Water Quality plus a Stormwater Pollution Prevention Plan reviewed by Sandy's Public Works Department before a building permit can be issued.
What happens if I violate the stormwater ordinance?
Public Works can issue a stop-work order or a written notice of violation demanding cleanup. A knowing or intentional violation is a Class B misdemeanor under Section 9-1-10, with each day of continuing violation charged separately, and the City can also assess a 25 percent penalty against a contractor's bond for remediation costs.

Sources & Official References

Other rules in Sandy

All Sandy rules

Compare Sandy to another location·View the Utah environmental rules overview

Get notified when Stormwater Management in Sandy, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Nearby Cities

How other cities in Salt Lake County handle stormwater management.

West Jordan, UT
Some Restrictions
Salt Lake City, UT
Some Restrictions
South Jordan, UT
Some Restrictions
West Valley City, UT
Significant Restrictions