Beaumont, CA Parking Rules: EV Charging (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit required
Yes, from the Beaumont Building Official
Review type
Administrative, nondiscretionary, health and safety only
Escalation
Conditional use permit under § 17.02.100 on written findings
Appeal
To the Planning Commission
Fees
Set by City Council resolution
Adopted
Ord. No. 1089, August 15, 2017

Summary

In the City of Beaumont, California, it is unlawful to install, operate or maintain an electric vehicle charging station without a permit from the Building Official. Review is administrative and nondiscretionary and limited to health and safety, with a conditional use permit possible only on a written finding of specific, adverse impact.

a.The Building Official shall implement an administrative review process to expedite approval of electric vehicle charging stations. Where the application meets the requirements of the approved checklist and standards and there are no specific, adverse impacts upon public health or safety, the Building and Safety Division shall complete the building permit approval process, which is nondiscretionary. Review of the application for electric vehicle charging stations shall be limited to the Building Official's review of whether the application meets local, state, and federal health and safety requirements. It shall be unlawful for any person to install, operate, or maintain an electric vehicle charging station without such a permit for such work, and the permit shall be secured from the Building Official by the owner or the owner's agent. ... e.Any permit approvals, which are granted pursuant to the provision of this Chapter, shall not authorize an applicant to connect the electric vehicle charging station to the electricity grid of the public utility. Any such connection shall be governed by the rules and regulations of the public utility.

Full Breakdown

Chapter 15.48 of the Beaumont Municipal Code, adopted by the Beaumont City Council as Ord. No. 1089 on August 15, 2017, creates a streamlined permit process for electric vehicle charging stations, following Government Code section 65850.7. It applies to all charging stations in the City. A station legally established or permitted before the ordinance took effect needs a new permit only if physical modifications materially change its size, type or components.

A charging station under § 15.48.030 is any level of electric vehicle supply equipment station designed and built in compliance with Article 625 of the California Electrical Code that delivers electricity from a source outside the vehicle into a plug-in electric vehicle. Under § 15.48.040, every station must meet health and safety standards imposed by the state, the City, the local Fire Department and the utility provider, plus the safety and performance standards of the California Electrical Code, the Society of Automotive Engineers, the National Electrical Manufacturers Association, and testing laboratories such as Underwriters Laboratories.

The Building and Safety Division must adopt a checklist of requirements for expedited review and can draw on the Plug-In Electric Vehicle Infrastructure Permitting Checklist and the Zero-Emissions Vehicles in California: Community Readiness Guidebook from the Governor's Office of Planning and Research. All documents must be posted on the City website, electronic submittal through the City's computer based plan review software must be offered, and electronic signatures are accepted.

Where an application meets the checklist and there are no specific, adverse impacts, the Building and Safety Division completes the nondiscretionary building permit approval. If the Building Official finds on substantial evidence a possible specific, adverse impact, written findings are required and the applicant can be sent to a conditional use permit under Section 17.02.100. That decision becomes final unless appealed to the Planning Commission. Any condition must mitigate the impact at the lowest possible cost. Permit approval does not authorize a grid connection, which the public utility governs. Fees are set by City Council resolution under § 15.48.070.

Violations & Fines

Section 15.48.060(a) makes it unlawful for any person to install, operate or maintain an electric vehicle charging station without the permit, which the owner or the owner's agent must secure from the Building Official. Chapter 15.48 prints no fine amount of its own. The Building Official has access to the permitted premises to inspect the progress of the work, and an unappealed adverse-impact decision becomes final.

Frequently Asked Questions

Do I need a permit to install an EV charger in Beaumont?
Yes. Section 15.48.060(a) says it is unlawful for any person to install, operate, or maintain an electric vehicle charging station without a permit for the work. The owner or the owner's agent must secure the permit from the Beaumont Building Official under the streamlined process in Chapter 15.48.
Can the city require a conditional use permit for a charger?
Only in a narrow case. Under § 15.48.050(f), if the Building Official determines on substantial evidence that a station could have a specific, adverse impact on public health and safety, the Official must make written findings and can require a conditional use permit under Section 17.02.100 of the Beaumont Municipal Code.
How do I appeal a Building Official decision on a charging station?
Section 15.48.050(f) says the Building Official's decision on an application becomes final unless it is appealed to the Planning Commission under the provisions of Section 17.020.030 of the Code. Any conditions imposed must be designed to mitigate the specific, adverse impact at the lowest possible cost.
Does the permit let me connect the charger to the grid?
No. Section 15.48.060(e) states that permit approvals under Chapter 15.48 do not authorize an applicant to connect the station to the electricity grid of the public utility. Any connection is governed by the rules and regulations of the public utility.
What fees apply to a Beaumont EV charging permit?
Section 15.48.070 says the City Council can establish fees by resolution for permits issued under Chapter 15.48. The chapter itself prints no dollar amount, so the current figure comes from the City's adopted fee resolution and the Building and Safety Division.

Sources & Official References

Other rules in Beaumont

All Beaumont rules

California rules heatmap·Compare Beaumont to another location·View the California parking rules overview

Get notified when EV Charging in Beaumont, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

EV Charging in Nearby Cities

How other cities in Riverside County handle ev charging.

Corona, CA
Some Restrictions
Menifee, CA
Light Restrictions
Moreno Valley, CA
Some Restrictions
Murrieta, CA
Some Restrictions
Palm Springs, CA
Light Restrictions
Riverside, CA
Few Restrictions
Temecula, CA
Some Restrictions