Pontiac, MI Parking Rules: EV Charging (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Trigger
More than 8 petroleum dispensing pumps
Requirement
At least 1 EV charging station
Multi-hose islands
Counted as multiple pumps
Applies to
Newly constructed filling stations, site plan
Section
Zoning Ordinance § 2.509(B)(6)

Summary

In the City of Pontiac, any automobile filling station with more than eight petroleum dispensing pumps must include at least one electric vehicle charging station. Zoning Ordinance Section 2.509(B)(6) counts a multi-vehicle fueling island as multiple pumps for purposes of hitting that eight-pump threshold.

6. All automobile filling stations with more than eight petroleum dispensing pumps must include at least one electric vehicle charging station. A petroleum dispensing pump is defined as the individual unit which dispenses petroleum-based fuel into a vehicle. A petroleum dispensing pump island that can dispense petroleum-based fuel to more than one vehicle at a time shall be counted as multiple pumps depending on how many vehicles can be fueled at a single time for purposes of this subsection (B)(6).

Full Breakdown

Pontiac's Zoning Ordinance regulates automobile filling stations in detail under Section 2.509(B), covering setbacks, separation from other stations and the R-1 District, truck turn analyses, landscaping, and lighting. Tucked into that list, Section 2.509(B)(6) requires any filling station with more than eight petroleum dispensing pumps to include at least one electric vehicle charging station as part of its site plan. The ordinance defines a petroleum dispensing pump as the individual unit that dispenses petroleum-based fuel into a vehicle, and it specifically addresses multi-hose fueling islands: an island capable of fueling more than one vehicle at a time counts as multiple pumps, based on how many vehicles it can serve simultaneously, when determining whether the eight-pump threshold is crossed.

This means a station cannot avoid the EV charging requirement simply by building fewer physical islands with more nozzles each. The requirement sits within the same subsection that requires newly constructed filling stations to submit a traffic impact study and a truck turn analysis with their site plan, all reviewed by the Planning Commission as part of site plan approval. Existing filling stations that predate the current ordinance and do not meet this or the other Section 2.509(B) standards are treated as lawful Type B nonconforming uses under Article 6, Chapter 5, and are not retroactively required to add a charger unless they expand or reconstruct in a way that intensifies the nonconforming use.

Violations & Fines

A newly constructed or expanded automobile filling station with more than eight petroleum dispensing pumps that omits the required electric vehicle charging station fails site plan review under Section 2.509(B)(6) and is subject to the Zoning Ordinance's general civil infraction penalties in Section 6.706, a minimum $100 fine plus costs for each day the noncompliance continues once identified.

Frequently Asked Questions

Do all Pontiac gas stations need EV chargers?
No. Only automobile filling stations with more than eight petroleum dispensing pumps must install at least one electric vehicle charging station, under Zoning Ordinance Section 2.509(B)(6). Smaller stations are not covered by this specific requirement.
How does Pontiac count pumps at a multi-hose fueling island?
Section 2.509(B)(6) counts a fueling island that can dispense fuel to more than one vehicle at a time as multiple pumps, based on how many vehicles it can serve at once, so a station cannot dodge the eight-pump EV charging trigger by consolidating nozzles onto fewer islands.
Does an existing Pontiac gas station have to retrofit an EV charger?
Not automatically. A filling station that lawfully existed before this requirement and does not meet it is treated as a Type B nonconforming use under Article 6, Chapter 5, and generally is not forced to add a charger unless it later expands or reconstructs in a way that intensifies the use.

Sources & Official References

Other rules in Pontiac

All Pontiac rules

Compare Pontiac to another location·View the Michigan parking rules overview

Get notified when EV Charging in Pontiac, MI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

EV Charging in Nearby Cities

How other cities in Oakland County handle ev charging.

Farmington Hills, MI
Light Restrictions